For Wagenborg we designed, built and installed a temporary access route from the quay to the jack-up drilling rig Grannos in the port of Eemshaven: a 16 m steel truss bridge and a stair tower that climbs about 10 m to the rig's deck. In the second quarter of 2026 we went from contract to delivery in about four weeks, covering engineering, procurement, fabrication and installation.

The challenge

The Grannos, owned by Dixstone, is in cold stack in Eemshaven. Personnel need safe access to the rig throughout the lay-up period. The rig lies about 16 m from the quay, with its deck about 10 m above quay level. The access route had to combine structural strength and stability with safe access. It also had to connect to the existing rig structure and be practical to install. The schedule left about four weeks for the whole job.

Our scope
Engineering and structural design of the access bridge, stair tower and support frame on the rig hull
Procurement of materials and equipment
Fabrication of the steel structures, together with our fabrication partner
Installation on site in Eemshaven
Engineering approach

The bridge is a welded steel truss with a grated walkway, handrails on both sides and a safety net slung underneath. It runs level from the quay to the stair tower, which takes personnel up the remaining 10 m to the deck. A support frame fitted to the rig's hull carries the stair tower and transfers its loads into the existing structure. All structures were designed to the applicable regulations and the relevant DNV standards. The connections to the rig and the quay were kept simple and robust, so everything could be installed quickly and removed later without permanent changes to the rig.

Result

The access bridge and stair tower were delivered and installed about four weeks after contract award. A schedule like that depends on short lines between everyone involved. Wagenborg, our fabrication partner and our own team worked as one project team from start to finish, and that cooperation made the deadline possible.

Key facts

Client: Wagenborg
Rig: Jack-up drilling rig Grannos (Dixstone)
Location: Port of Eemshaven, NL
Structures: Truss access bridge (≈ 16 m), stair tower (≈ 10 m), support frame
Scope: Engineering, procurement, fabrication, installation
Lead time: ≈ 4 weeks, contract to delivery
Period: Q2 2026
Rules: Applicable regulations and relevant DNV standards